Scheduling Inspections
-
All inspections are to be scheduled one day in advance; the inspection will be scheduled at the earliest available date.
-
You will schedule an inspection through your permit within Cloudpermit.
-
Select your permit and scroll down to inspections, you will locate the type of inspection you need to request.
-
Select Request Inspection
Then select date of the inspection.
-
All cancellations must be done before 8 a.m. on date of inspection.
-
Inspections can be scheduled separately.
-
Before the framing inspection can be scheduled, all other trades must be completed and signed off.
-
When scheduling an inspection, be sure inspection is ready at the time of request.
-
Foundation survey must be on file prior to scheduling a floor system inspection or any rough-ins for slab homes. Surveys must be in the office by 2 p.m. two days prior to scheduled inspection.